Reorder point & EOQ calculator
When to reorder (reorder point) and how much (economic order quantity) under the classic EOQ assumptions.
Result
How it’s calculated
- Reorder point = daily demand × lead days + safety stock
- EOQ = √(2 × annual demand × order cost ÷ holding cost)
Worked example
Inputs: 20/day, 7 days, safety 30
Result: Reorder at 170 units
Good to know
- EOQ assumes steady demand and constant costs; adjust for MOQs, price breaks and seasonality.